Electrical Safety Program: What Goes In It and Where the Rules Come From

Updated July 23, 2026

No OSHA standard is titled "electrical safety program," but the duties one collects are mandatory. On construction sites they come from 29 CFR 1926 Subpart K: ground-fault protection under 1926.404, safe work practices near energized parts under 1926.416, lockout and tagging of circuits under 1926.417, and guarding of live parts under 1926.403. A written program pulls those duties, plus PPE selection and training, into one document, which is exactly what GCs and prequal reviewers ask trade contractors to produce.

Generate my Safety Program for $149See a full sample first

The elements reviewers look for

Program elementWhere the duty comes from
GFCI protection or an assured equipment grounding conductor program for temporary power29 CFR 1926.404(b)(1)
Cord and equipment condition: no worn or frayed cords, cords protected from damage29 CFR 1926.416
No work near energized parts unless workers are protected; barriers and guarding29 CFR 1926.416 and 1926.403
Deenergizing, lockout, and tagging of circuits before work on them29 CFR 1926.417 (construction); 29 CFR 1910.147 for servicing your own equipment
Temporary wiring and lighting installed to the standard29 CFR 1926.405
PPE selected from a documented hazard assessment29 CFR 1910.132
Training crews to recognize and avoid electrical hazards29 CFR 1926.21

Every trade needs this, not just electricians

Electrocution is one of the OSHA Focus Four, and the everyday exposures are not wiring work: damaged extension cords, missing GFCI protection on temporary power, tools used in wet conditions. If your crew plugs in a saw, the GFCI and cord rules in Subpart K apply to you, and a reviewer will expect your program to say how you meet them.

For electrical contractors the bar is higher. Reviewers expect the program to state when circuits are deenergized before work, how lockout and tagging is applied under 1926.417, and who is qualified to work near energized parts.

Where arc flash and NFPA 70E fit

OSHA’s electrical standards set the legal duties, and NFPA 70E is the industry consensus standard most GCs and safety managers use for the details of energized work: justifying it, permitting it, and choosing arc-rated PPE. NFPA 70E is not itself an OSHA regulation, but a program that ignores it will draw questions on any commercial site, so most written programs reference it for energized work procedures.

Why a blank template does not survive review

A downloaded template gives you headings. Reviewers look for your voltage classes, your equipment, your GFCI method (breakers, cord sets, or an assured grounding program with tested and color-coded cords), and citations that exist. A program that never says who is qualified and who is not reads as unfinished, because it is.

TailgateDocs generates a Written Safety Program built for your trade for $149, with every citation checked against a verified OSHA standards table before delivery, and free revisions within 24 hours if a reviewer asks for changes.

Common questions

Does OSHA require a written electrical safety program?

No standard names one, but the underlying duties are mandatory, and several of them, like the assured equipment grounding conductor program under 1926.404(b)(1), must be in writing themselves. GCs, ISNetworld, and Avetta routinely require a written electrical safety program from trade contractors regardless.

What is the GFCI requirement on construction sites?

Under 1926.404(b)(1), 120-volt, 15- and 20-amp receptacles that are not part of the permanent wiring must have GFCI protection, or the employer must run an assured equipment grounding conductor program with documented cord inspections and tests.

Is NFPA 70E training required by law?

NFPA 70E is a consensus standard, not an OSHA regulation. OSHA cites the hazard under its own electrical standards, and inspectors and GCs treat NFPA 70E practices as the recognized way to control energized work, so most commercial sites require it by contract.

Do I need this if my electricians are licensed?

Yes. Licensing covers the person; the program covers the company: how circuits get locked out, how cords are inspected, what PPE is issued, and how crews are trained. Reviewers ask for the document, not the licenses alone.

Official sources

Skip the template. Get the finished document.

1,200+ documents generated for 350+ contractors. Verified citations, ~4 minute delivery, free revision within 24 hours if a reviewer asks for changes.

More on written safety programs

OSHA Safety Manual for Construction CompaniesEmergency Action Plan: What OSHA Actually RequiresWritten Hazard Communication Program for ContractorsSite-Specific Safety Plan vs Written Safety ProgramOSHA self-inspection checklist

Keep exploring

Lockout/tagout program requirementsWritten safety program template structureThe OSHA Focus Four hazardsOSHA requirements for small contractorsWritten safety program ($149)State requirements quizFree toolbox talks (EN/ES)Sample documentsSafety Program for RoofingSafety Program for ElectricalSafety Program for HVAC / MechanicalSafety Program for General Contractor